A liner change often fails the shutdown window for a simple reason:
the stop starts before the kit, the lifting plan, or the go/no-go wear
check is actually ready. This page is a preparation checklist
for a planned crusher liner replacement
— what to confirm
before isolation, what to stage at the machine, and what to record so
the next window is easier to plan.

It is not a cost model and not a machine-specific installation
manual. Follow the site isolation procedure and the machine
documentation for removal, torque, consumables and restart. This article
does not give tightening values, backing-compound recipes or lifting
capacities.

What this page
covers — and what it does not

Use this page when the job is: get a liner set through a
planned stop without discovering missing parts or an unresolved wear
decision at the gate.

1. Decide whether
this stop is the right window

Treat “change liners” as a decision with evidence, not as a slogan on
the shutdown board.

Check What to review before freezing the date If it is still open
Remaining wear Thickness or wear-mark readings at the agreed points, plus photos of
high-wear zones and seating areas
Do not assume the set will “probably last one more campaign” without
a recorded review
Mating set Whether the mantle and concave, or the corresponding jaw / cheek
set, should be changed together
A single leftover liner can still force an unplanned return stop —
record the reason if one piece will be retired early
Lead time vs gate Confirmed identity, quantity, destination and a written need-by date
against the shutdown gate
See casting
MOQ and lead time
for planning factors; do not invent a standard
shipping day-count
Access and lifting Crane or hoist window, dropped-object zone, and whether two crews
can physically work around the same machine
A schedule that fits on paper may not fit around the crusher
Mandatory vs optional work What must finish for a safe restart, and what can be deferred in
writing
Opportunity tasks should not block the critical path

Previous campaign hours, tons and removal reasons belong in the cost-per-ton
log
. Use them to judge whether the next interval is realistic. Do
not convert this preparation page into a second cost worksheet.

2. Freeze a work
package, not a one-line task

Write a short scope register for the machine and the stop. Each line
should name the equipment, the exact position, the parts and
consumables, the special tools or lifting gear, the access need, and the
person who can sign the job complete.

Package line Record before the gate
Machine and position Plant tag, crusher model, chamber or jaw position
Liner identity Part name, complete part number or agreed model-match reference,
revision if used, left/right or upper/lower where applicable
Set scope Full set or named positions; pieces per set
Associated items Fasteners, locking parts, specified consumables, lifting lugs or
other items only if they are required by the machine
documentation or the agreed order
Exclusions Anything assumed by the crew but not on site or not on the
order
Tools and access Torque tooling specified by the machine instructions, lifting gear,
scaffolding or platforms
Restart owner Who confirms isolation release, guards and a controlled return to
feed

Do not copy a generic bill of materials from another machine. If a
consumable, fastener or seal is not required by the applicable
instructions or the agreed order, leave it off the package rather than
adding it “just in case” under a vague description.

3. Stage and verify
the kit before isolation

Open the kit in a controlled area before the machine
is isolated, early enough to fix a shortage without burning the
window.

Staging check Pass looks like Hold if
Identity Markings or packing identity match the frozen scope line The stamp, tag or packing list disagrees with the order
Quantity and set completeness Every agreed position is present A “set” arrives short, or left/right parts are not
distinguished
Condition No transit damage that affects seating or lifting points Cracked lugs, bent seats or unusable packaging for a precision
face
Handling Lifting points and mass are known from the supplier or machine
information you actually have
The crew would have to guess a lift
Documents The packing list and any agreed inspection records arrived with, or
clearly ahead of, the goods
Required records are missing — see the quality-documents
checklist
Storage Parts sit in the agreed lay-down, labeled by position, protected
from contamination
Parts are mixed, unlabeled, or stored where they can be taken for
another job

Supplier packing identity is covered in more detail on the packing
and dispatch checklist
. This step is the site’s confirmation that
the staged kit matches the shutdown package.

4. Keep
installation and restart inside the site procedure

This section is a readiness reminder, not a substitute for lockout,
permits or the machine manual.

  • Isolate and test for dead under the site procedure.
    Do not treat a webpage as authorization to start work.
  • Once the chamber is safe to enter, inspect seating faces, fasteners
    and any damage that would prevent a correct fit. Photograph conditions
    that may explain the last campaign’s wear pattern.
  • Install and tighten according to the machine
    documentation
    . This page does not publish torque values or
    consumable mix instructions.
  • Mechanical completion is not production readiness. Use a signed
    restart list: tools and temporary supports removed, guards and
    interlocks restored, fasteners and locking devices checked, chutes
    clear, people accounted for, isolation released in a controlled
    way.
  • Return to feed under the approved plan. Watch for abnormal noise,
    vibration or temperature and stop if the site criteria require
    inspection.

If a seating or fit question cannot be closed, keep the machine out
of service until the responsible technical person records a disposition.
Do not “make it fit” against an unresolved measurement. Fitment disputes
that start from missing drawings belong on the fitment
proof
page, not in an improvised shutdown workaround.

5. Hand the next
planner a complete record

Before the crew leaves the job, capture what the next shutdown and
the cost log will need.

Record Why it matters later
What was installed Part identity, positions, quantity, and any deviation from the
frozen scope
What was removed Wear photos, failure or wear-out tag, and whether the run was
complete
Operating context Hours and tons for the removed set, if measured; feed or setting
changes worth noting
Deferred work Defects left in place, with a due date or next inspection
trigger
Actual duration and delays Waiting for parts, access or a decision — so the next plan is
honest

Enter hours, tons, costs and failure tags in the cost-per-ton
tracking sheet
. This preparation page only makes sure those inputs
are collected while the evidence is still in front of the crew.

FAQ

Is a
liner change just a maintenance task on the shutdown list?

It is a work package. If parts, lifting, access and a go/no-go wear
review are still open, the date on the board is not yet a plan.

Should
every liner in the chamber be changed at the same stop?

Not automatically. Review remaining wear on the mating parts and the
cost of an extra stop if one liner is left in service. Record the reason
if you retire a piece early or defer one position.

Can I use this
checklist for VSI tips and anvils?

Use it only for the shutdown-planning frame (window, staging,
isolation, records). For the VSI wear path, triggers and kit RFQ, use
the VSI
replacement checklist
.

Does
this page tell me how much a liner change should cost?

No. Compare sets with a consistent cost scope on the cost-per-ton
page
. Preparation quality affects downtime, but this article does
not calculate savings.

What if
the new liners have not arrived when the gate opens?

Do not start a liner job on a partial, unverified kit unless the
responsible person records a reduced, safe scope. It is usually better
to defer the liner task in writing than to isolate the machine and then
wait.

Who decides
tightening, consumables and lift plans?

The machine documentation, the site lifting rules and the competent
personnel on the job. This article does not replace those
instructions.

For a liner set that must arrive before a planned stop, email
info@gubtcasting.com or
use the contact form.
Send the part number or model-match details, the positions in the set,
the quantity and the shutdown need-by date. GUBT can review the identity
and quotation scope; installation remains a site responsibility.